Vertical Start-up for Millions of Revenues for large paper manufacturer facing an investment in a new paper machine

Client situation & approach

Our client is a large paper manufacturer facing an investment in a new paper machine, increasing their capacity tremendously. By integrating Project Management, Early Equipment Management and WCOM-methodology the investment project reached exceptional results and went beyond the purchase of the new machine and involved the restructuration of the entire mill.

Results

  • 3 % of OEE vs. budget
  • Start-up lasted half the time in comparison to the benchmark in the group
  • Generated five million EUR additional revenue in the first ten months